PLANNING MILESTONES (listed in reverse chronological order)
September 2005:
This was the month that finally saw all of the Bracken staff together again on the same floor. The last of the hoarding
disappeared, and the final version of CHEER was unveiled as Document Services staff moved into their new office.
Within hours on the first day of term, every available chair was filled with students turning Bracken Library and CHEER into
the exciting, interactive space it was intended to be. The group rooms have also been put to good use by both instructors
and students from across the Faculty of Health Sciences.
The Videoconference Room was completed, and will provide Botterell Hall
with an attractive and high-tech space for outreach and distance
education.
August 2005:
In August, most of the Bracken staff returned to the Main Floor and took up residence
in the new CHEER space. Staff in Administration, Public Services, Technical Services and Access Services
all began to get used to the new, bright and very inviting space.
We were also pleased to invite faculty, staff and students into CHEER, though we all had to contend with unfinished
rooms, lack of air circulation, heat pump leaks and temperamental computers and printers.
As Access Services moved into the new Circulation and Reserve space, new hoarding went up and we all listened as the
old circulation desk was dismantled to make way for Document Services' new office.
Planning continued in earnest for Alumni Weekend (September 23-25) as well as the CHEER grand opening event scheduled
for October 21, 2005.
June and July 2005:
Early summer saw us working with the architect and project manager to approve paint colours, detailing and adjustments
to the millwork. There was also a constant stream of questions from the contractors as they began to actually create CHEER
from the mass of architect and designer drawings.
Decisions were made regarding the audiovisual and computer requirements for the e-Laboratory, the Small Group Rooms and
the Videoconference room.
Bracken joined a Queen's University Library project to develop an online room booking system. When completed it will allow
faculty, staff and students in Health Sciences to pre-book rooms in CHEER.
May 2005:
In April and May the furniture quote was finalised
for the staff offices, small group rooms, the computer lab, discussion
areas, the open area computer stations, and the videoconference room.
Staff started to work on signage for spaces, rooms and directional signs.
This included lively discussions on what to name these spaces.
The walls were prepped for painting.
April 2005:
The floor was emptied from floor to ceiling during March and April.
In April, the SUN equipment was finalised and the
SUN Education Grant was approved which gave us one free piece of equipment
for every one purchased. (There will be 30 SUN Rays in CHEER.)
March 2005:
Construction start date: March 14/2005.
A separating wall was constructed to allow the library to remain open during
construction.
February 2005:
Reference and Circulation desk designs finalized.
Public and staff areas of the main floor in Bracken start relocating to
the lower level. This includes the construction of some temporary space
to accommodate staff.
December 2004:
October 2004:
September 2004:
July 2004:
June 2004:
May 2004:
Meetings with Core Planning Team held on May 20 and 28, 2004.
Staff teams finalized.
Poster prepared for presentation at ACMC Annual Meeting in Halifax, NS.
Meetings with Advancement and Stantive Solutions (SUN).
January 2004:
December 2003:
November 2003:
Presentation of CHEER concept to School of Rehabilitation Council.
October 2003:
May 2003:
April 2003:
March 2003:
January - February 2003: